HOTEL SUGICHO is currently under construction for the opening of spring 2022.Please look forward to it.
HOTEL SUGICHO
075-241-0106
New construction scheduled to open in March 2022!

【Official】HOTEL SUGICHO

HOTEL SUGICHO is currently under construction.

 It opened in 1966 and we thank you for your patronage for 54 years.
Over 50 years have passed since the construction of HOTEL SUGICHO, and in consideration of the facilities and earthquake resistance of this facility, it will be newly built by March 2022.Over a half century, more than 1.5 million guests have stayed.Please look forward to the HOTEL SUGICHO"HOTEL SUGICHO" so that you can make use of that experience and make your life comfortable, safe and enjoyable.


About new construction

  • Notifications

    ·We are continuing to improve the ground and foundation work.In addition, we have obtained permission for procedures necessary for proceeding with construction, such as building confirmation.

    ·The investigation of the buried cultural properties associated with the new construction has been completed.There was no delay due to the investigation.

    ·In March 2022, we have been visiting the group customers since the opening.
    Currently, we are checking the state of construction from the main street, and we will explain the progress of construction and the facility after new construction at the temporary office.
    If you would like a preview, please apply to the office.
    Tel:075-241-0106
    mail:sugicho@kyoto-ryokan.jp

State of the latest construction

  • I went to witness a quality inspection of steel frames

    I went to witness the quality inspection of the steel frame used for future construction work.
    The grade of the steel frame factory is H rank, so there is no company near Kyoto, so we will get it from the factory in Kaizuka, Osaka.
    I was surprised at the number and size of the steel frames, and realized that these steel frames became the backbone of building materials.
    Of course, I have also witnessed the inspection.
  • State of construction in April

    Scaffolding is installed while pouring concrete into the foundation.
    It seems that the scaffolding is raised while waiting for the concrete to harden, and the steel frame is placed there.
    From now on, concrete parts will be piled up every month.

    Construction is proceeding smoothly as planned.
  • State of construction in March 2021

    We are in the process of digging the ground to the depth required to build a disaster-resistant building and creating a strong ground.
    You may be worried that the building work has not been started yet, but the ground and foundation work will be done over time to ensure completeness.
    The process is proceeding smoothly as planned toward completion.

State of construction so far

  • State of construction in February 2021

    The dismantling of the underground part and the earth retaining work are almost completed, and the foundation work is underway.
    (The dismantling and earth retaining work of the partially built-up part is ongoing.)
    There is a lot of spring water, but unfortunately it was not a hot spring.

    The investigation of the buried cultural properties has been completed.In addition, various notifications are proceeding smoothly.
    The construction is almost as planned.

  • State of construction in December

    Finally, we started dismantling the underground part and foundation work around it.
    The groundbreaking ceremony has just finished and it has just come to an end.
    The earth retaining work will take until the end of January next year, after which the construction work is scheduled to begin.

    Construction is proceeding as planned.
  • Demolition work up to the 1st floor will be completed in November!

    We are currently dismantling the 2nd and 1st floors.
    Finally, next week, we are planning to finish the demolition work and hold a groundbreaking ceremony.
    It took more than four months to start dismantling, but I was finally able to start the foundation work.
    This month, we have just begun to select the layout of the dining venue, chairs, and tables in this facility.

    Construction is proceeding slightly earlier than planned.


    ※Pamphlets, meal menus, floor plans, and model room allocations for educational travel facilities can be found on the download page by moving from the educational travel tab above.

Progress information

  • October progress

    We raised the heavy equipment and started dismantling from the 5th floor.
    The 5th floor is over and the 4th floor is being dismantled.
    We plan to demolish up to the first floor in November.
  • The dismantling work is still underway in September!

    I don't know what it looks like anymore, but this is a photo of the front desk area during disassembly.
  • Demolition work started in July.

    The dismantling work has finally started.(Scheduled until December)

    Please move from the above educational travel tab for facility guides, menus, and floor plans for newly constructed educational travel.

Access

Google Map

Hotel Name

HOTEL SUGICHO

Address

172 Moriyama Town, Oike-agaru, Tominokoji-dori, Nakagyo Ward, Kyoto City, Kyoto Prefecture

Telephone number

075-241-0106

Notes

JR Kyoto Station, get off at Karasuma-Oike Station (3 stops from Kyoto Station) on the Municipal Subway Karasuma Line, and a 7-minute walk from the first exit

About 15 minutes from Meishin Expressway, Kyoto East Interchange or Kyoto South Interchange to For Kyoto City
※In case of car There is no private parking so we will introduce coin parking at the front desk after arrival.(We will notify you after searching the available space on the internet.The charge is around 2,000 yen at 10 o'clock the next morning.)
Go to the traffic access page

Reserve·Contact us

Please feel free to contact us if you have any questions.